Change Order <br /> No. 05 <br /> Date of Issuance: December 28,2022 Effective Date: December 28,2022 <br /> Project: County Horton Park Pool Owner:Lee Coun Owner's Contract No.:2114-8123 Horton <br /> Improvements—Bathhouse Reno Park Sanitation Facility <br /> Contract: 1 IDate of Contract:June 06,2022 <br /> Contractor:JM Thompson Company (Engineer's Project No.: 21.01705 <br /> The Contract Documents are modified as follows upon execution of this Change Order: <br /> Description: <br /> Project cost increase due to masonry work along the walls of the existing building. The work associated with Change Order No.5 will <br /> rectify the issues included within RFI No's.Seven(7)and Eight(8). This change order work will be defined as a cost not to exceed <br /> proposal. Should the mason determine that the existing brick section located between the two northern doorway entrances can be <br /> repaired,rather than rebuilt,this will result in the CO cost decreasing by$1,100.00. <br /> Attachments(list documents supporting change): <br /> Change Order Summary with all back-up documentation <br /> CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: <br /> Original Contract Price: Original Contract Times: ❑ Working days ® Calendar days <br /> Substantial completion(days or date): 100(Oct.04.2022) <br /> $ 737,115.90 Ready for final payment(days or date): 110(Oct 14.2022) <br /> [Increase] [Decrease] from previously [Increase] [Peemase] from previously approved Change Orders <br /> approved Change Orders No. I to No. 4: No. 1 to No. 2: <br /> Substantial completion (days): 89 <br /> $ 100,513.11 Ready for final payment(days): 89 <br /> Contract Price prior to this Change Order: Contract Times prior to this Change Order: <br /> Substantial completion(days): 189 <br /> $ 837,629.01 Ready for final payment(days): 199 <br /> [Increase] [Decrease] of this Change Order: [!Rffease] [Deerease] of this Change Order: <br /> Substantial completion(days or date): 0 <br /> $ 9.816.40 Ready for final payment(days or date): 0 <br /> Contract Price incorporating this Change <br /> Order: Contract Times with all approved Change Orders: <br /> Substantial completion(days or date): 309(Mav 01.2023) <br /> $ 847,445.41 Ready for final payment(days or date): 319(Mav 11.2023) <br /> RECOMMEN D: ACCEPT,hDK ACCEPTED: <br /> Engineer(Authorized Signature) �wner(Authorized <br /> /Signature) Contractor(Authorized Signature) <br /> Date: 12/28/2022 Date: �— (Z �'l��_% Date: <br /> This instrument has been preaudited in the <br /> Approved by Funding Agency(if applic f required by the Local Government Date: <br /> 0 adge4andFF' Contract Act. <br /> Prepared by the Engineers Joint Contract Dot liQ&4GQVQ;Ae Construction Specifications Institute. <br /> Page t of i <br />